Solar, Wind, & Hydro Interconnections

7 Steps to Completing Your Interconnection Project

*Members, all applications submitted after December 1, 2025 will fall under Plumas-Sierra Rural Electric Cooperative’s (PSREC) NEM 3.0 program.

1. Sizing Your System & Verifying Your Program Eligibility

Sizing

  • All systems must be sized to be equal to or less than the members’ last 12 months of usage.
  • If you do not have 12 months of usage or the home is a new construction project, your system
    can be sized using the equation of 2 watts per livable square foot.
  • Proof of square footage must be submitted.
  • 12 months of members’ usage history can be requested by contacting PSREC at (530) 832-4261.

Program

  • Systems up to 9.9kW will be eligible for the NEM 3.0 program.
  • As of December 1, 2025, all applications will fall under the NEM 3.0 program.
  • Attachments D & H in the Interconnection of Distributed Resources Policy and Procedure Manual.

2026 generation pricing for all NEM members: $0.04

    • Systems 10kW and above will be eligible for the Co-Energy program.
    • Attachments E & I in the Interconnection of Distributed Resources Policy and Procedure Manual.
    • Contact PSREC at (530) 832-4261 to verify which interconnection program you qualify for.

2. Get Contractor Quotes

3. Submit Your Application to the PSREC Interconnection Department

  • Member or contractor submits complete application
  • System design included
  • Electrical one-line drawing included
  • Applicable fees included

4. Application Review

    • Submit application at least 6 weeks prior to proposed interconnection
      (10 weeks for 400 Amp or commercial service).
    • PSREC reviews application for completeness and accuracy.
    • Any required corrections must be made by the member or contractor.
    • Applications will be reviewed and responded to within 15 business days.
    • Construction may begin after application approval.
    • Notify PSREC and provide an estimated installation completion date.

5. System Installation

    • Contractor installs the system.
    • The system can not be energized until the meter is exchanged.

6. City or County Conducts Building Code Inspection

    • Member or contractor obtains local jurisdiction inspection.
    • Send inspection notification to PSREC.

7. PSREC Inspection & Meter Change Out

    • Submit a copy of the final building permit showing approved inspection.
    • Call PSREC to schedule a meter exchange (may take up to 10 business days).
    • PSREC personnel will inspect the system for compliance with PSREC standards.